The project is planning the expansion of the existing Hamburg Refinery, by adding the following process units and facilities: HVO Unit, pre-treatment Unit, tank farm balance (tanks partially supplied by others), interconnecting lines, new electrical substation and rack room, interconnecting cables between new substation building and existing substation and control room.
In home office (whenever possible) he/she shall cooperate with the project team for constructability and feasibility studies, with APPAL for technical tabulation of the civil bidders’ proposals and clarification meeting with the bidders, with civil department to analyze/define the work requisition to be included in the subcontractor scope of Work.
Each supervisor reports to the construction manager.
He/she directs subcontractor activities for his own discipline, ensuring that plant construction works are performed according to the erection schedules and project documents, within the assigned cost budget, and according to quality & safety procedures, as well as according to the terms and conditions of the subcontract.
One or more assistants may support him/her.